Architectural Design Process: 7 Key Phases From Concept to Construction

Quick puzzle. In which design phase do most architects make about 40% of the profit while not alerting most clients? Construction documentation. Sketch owners adore and avoid paperwork.

The architectural design process has seven steps that take a building from concept through design to completion. Each phase concludes with client sign-off, which locks in the decisions made before the next phase.

That discipline matters. McKinsey research shows that large construction projects typically take 20% longer than scheduled and run up to 80% over budget. The best lines of defence against those numbers are clear phases, written approval, and early decisions which are possible with reliable architectural designs.

This guide explains every phase, the deliverables you receive, decisions you make, realistic timelines and building permit rules in Oman. It also includes a project example and a checklist for choosing a design partner.

Key takeaways

  • 7 phases: pre-design, schematic design, design development, construction documentation, building permits, bidding and negotiation and construction administration.
  • Biggest fee share: The percentage of the design fee for construction documentation is around 40% or 35 to 50%.
  • Typical design time: Usually takes about 10 to 20 weeks or more to design a small residential project before permits and construction.
  • Oman permits: For a major building permit, the processing time for municipal permits in Oman is listed on the Ministry of Interior’s technical services page as 3 to 10 working days. Other approvals can introduce time delays.
  • Oman Building Code: Voluntary for 2026 to 2027, gradual enforcement for new buildings in Muscat from 2028, mandatory for new buildings throughout Oman from 2030.

What Is the Architectural Design Process?

The architectural design process is the systematic progression of tasks that converts a client’s brief into an acceptable, constructible and manageable building. Architects establish objectives, build a concept, manage engineering, create architectural plans, secure building permits and assist in the building. Each stage concludes with the client’s sign-off.

Why the order matters. In 2004, architect Patrick MacLeamy crystallised the concept of cost and function. As a project proceeds, your leverage to affect cost and function increases as your leverage to affect the cost of a change decreases. Rework shows the price of late changes. Delta Gulf Overseas provides all the steps in this guide via its Architectural Design Services in Oman.

Who Is Involved in the Architectural Design Process?

The building project requires a team and each member arrives at a different time. The client takes charge of the team and the architect is the one guiding the team. The table lists what they do and by whom.

Role What they do When they join
Client or owner Sets the brief and budget, answers questions and approves each phase. Pre-design
Architect Leads the design, coordinates consultants and issues architectural drawings. Pre-design
Structural engineer Sizes foundations, columns and beams. Involves structural engineering early. Schematic design to design development
MEP engineers Design cooling, electrical, plumbing and fire systems. Design development
Interior designer Resolves finishes, joinery and lighting through our interior design team. Design development
Quantity surveyor Checks cost at every stage. Ask a quantity surveyor for an early estimate. Pre-design onward
Project manager Controls cost, schedule and risk across all phases. Pre-design onward
Authorities and utilities Review plans and issue approvals, including the municipality, Civil Defence and Nama. Permit phase
Contractor Prices and builds the project. After bidding or earlier in design-build
Supervision consultant Observes the build against the design and approved drawings. Construction

These parties are aligned through a project manager. Our Construction Project Management service outlines the role from inception to handover, while our guide to the 10 Primary Project Manager Roles and Responsibilities in Construction gives you a good idea of the roles you’re likely to encounter.

A single rule to save weeks: name a single decision-maker for a client. Committees delay and revoke agreed-upon decisions.

Ready to Start Your Next Construction Project?

Book a consultation today to discuss your project requirements and get started with the right estimating support.


Book a Consultation

7 Key Phases of the Architectural Design Process

The seven phases are sequential. These seven phases are listed below.

Phase-by-phase deliverables table

Take a look at this table to see the outcomes of each phase and what it is asking of you. The typical fee shares from Bob Vila and Fontan Architecture are listed below. They will differ for different regions, the type of project and an appointment date, so these are guidelines and not a quote.

Phase Core question Main deliverables Your key decision Typical fee share
1. Pre-design Does the project make sense? Site analysis, zoning check, space programme, feasibility notes, project brief Approve the brief and budget About 5%
2. Schematic design What will it look like? Two or three concept options, site and floor plans, massing, 3D architectural visualization, preliminary cost estimate Pick one concept 15 to 20%
3. Design development How will it work? Coordinated plans, sections and elevations, material schedules, structural and MEP layouts, updated cost estimate Approve materials and systems 10 to 20%
4. Construction documentation How do we build it? Full set of architectural drawings, structural and MEP drawings, door, window and finish schedules, written specifications Sign-off drawings and specifications About 40% (35 to 50%)
5. Building permits Is it legal to build? Permit drawings, authority approvals, building permit Authorise the permit submission Varies by scope
6. Bidding and negotiation Who builds it, and for how much? Tender package, bid comparison, contractor recommendation, contract Choose the contractor About 5%
7. Construction administration Does the build match the design? Site observation reports, submittal reviews, change orders, payment certificates, punch list, completion certificate Approve changes and payments 20 to 25%

Phase 1: Pre-Design Phase

Riddle: What phase of the project doesn’t have any drawings but has the largest influence on the budget? The pre-design phase. It determines if the project is viable before anyone draws a line.

The architects require the following documents for the pre-design phase:

  • Land documents: proof of ownership, the cadastral drawing (krooki) and the site plan. These are requested by Muscat’s permit to commence service.
  • Space requirements: room, area and space for expansion.
  • Budget range: a realistic figure and a funding timeline.
  • Performance objectives: cooling, shading, privacy, parking and expansion.
  • Deadline drivers: the date that you have to open or move in.

The phase concludes when the project brief is signed off. A brief will include these points: Purpose, Space Schedule, Budget and Funding, Programme, Quality Level and Sustainability Goals. The architect compares all subsequent sketches to it. Bob Vila says that the fee for pre-design typically covers about 5%.

  • Your part: provide the documents, be honest about your budget and let someone else represent you.
  • Approval checkpoints: Sign the brief and budget.
  • Discuss with your architect: what are the risks on this site? What can I afford?
  • Common error: equating pre-design with a formality. The phase never feels real and teams rush it with the pressure rising in the schematic design phase, Factorapp warns.

Phase 2: Schematic Design

Three sketches. One decision. In a nutshell, schematic design. The architect converts your brief into a concept: Massing, Floor plan, orientation and rough elevations. PlanSignals says that there are two or three options to compare.

This is the part where 3D architectural visualization comes into its own. Simple walk throughs and rendered views allow you to make scale, light and street presence judgments before committing. Here facade concepts are realised and exterior design is demonstrated.

Deliverables: sketches of site and floor plan, rough elevations, 3D massing views and preliminary cost estimate. This portion is 15 to 20% of the breakdown for Bob Vila.

  • Your task: to compare options with the brief and then select one.
  • Approval checkpoint: you sign the selected concept and include the cost estimate. You don’t have any choices to refer to when you consider decisions three phases later, warns Factorapp.
  • Discuss with your architect: why you didn’t choose the other possibilities? What is the impact of each option on cost?
  • The common pitfall: Approving a concept over the phone or chat. Have a written clearance.

Phase 3: Design Development

Schematic design is used to illustrate what you will construct. It is made through design development. The team identifies materials, scales the structure and arranges building systems. The equivalent stage 3 is called “spatial coordination” by RIBA. It tries out the concept and leaves it essentially the same.

Coordinated Plans, Sections and Elevations, Material and Finish Schedules, Structural and Mechanical, Electrical and Plumbing (MEP) Layouts and an updated cost estimate will be provided. This is a 10 to 20% fee for this phase.

It’s also your final opportunity to second-guess. Once the design is developed, any change will cascade through the drawings, as displayed on the MacLeamy Curve. Interior finishes, joinery and lighting lock in here; time to call the interior designer.

  • Your part: look at samples and options of systems, then freeze the scope.
  • Approval checkpoint: Sign the design freeze. Use it like a gate and reopen it only for a good reason.
  • Question your architect: What decisions are still open and what are the fees?
  • Common mistake: changing the finishes after the design freeze. Late swaps require revisions in all disciplines.

Phase 4: Construction Documentation

Construction Documentation showing architectural drawings, building plans, specifications, and approval checkpoints.

Another puzzle. Which phase is the biggest chunk of the fee but gives the least exciting images? Construction documentation beats again. These architectural drawings and specs provide the contractors with all they require to estimate and build. The phase will cost approximately 40% of the fee, usually 35 to 50% as per Fontan Architecture.

The most detrimental lack here is gaps. At the latest design phase, unresolved questions and notes are not absorbed, according to Learn Architecture. Typically, a complete set will consist of:

  • Architectural plans, sections, elevations and details
  • Plans and drawings for structures and services
  • Door, window and finish schedules
  • Written specifications

Run a closeout check before this phase begins and write down all open design decisions as Factorapp recommends. When your ideas are approved, it is transformed into a buildable sheet by accurate design and drafting. Specifications that are clear clarify which materials the contractors will need to price.

  • Your role: You are the answerer and identifier of scope gaps in the set.
  • Approval checkpoint: You sign the complete drawing package and specifications.
  • Inquire from your architect: Are all design questions answered? Are the drawings in accordance with the specifications?
  • Mistake to avoid: beginning with options. All design development questions that are not answered go here.

Phase 5: Building Permits

No site work, no permit. Unauthorised building will be met with penalties, including the potential for demolition, as warned by Muscat Municipality in August 2025. Plan permit time into your schedule and prepare a complete submission by getting help from professional master plan and permit drawings service.

The owner, plot and consultant enter the details of the application and documents are submitted by the consultant. Maps are submitted to municipal engineers who then review them and the application is filed with fees and the municipal director approves. The list of documents and approvals below covers the section on Oman.

  • Your role: approve the submission, pay fees and monitor the comments from the municipality.
  • Approval checkpoint: you approve the permit application.
  • Questions to ask your architect: What other approvals are required in addition to the Municipal Licence?
  • Common error: thinking that one permit is good all the way up to the end of the day. Any changes or additions to the building or its use are subject to the same permit requirements as the original building and are covered by the same permit.

Phase 6: Bidding and Negotiation

Not all the lowest bids are the lowest prices. Bidding is a tool to transform drawings into contractor rates. Tendering is part of the core service of an architect under AIA and RIBA appointments that takes up approximately 5% of the fee, according to Illustrarch.

  • Distribute tender package.
  • Answer bidder queries.
  • Make line-by-line comparisons of bids.
  • Discuss services and fees.
  • Award the contract.

Look at scope, exclusions, programme and provisional sums as well as totals. Your delivery route, coupled with strong tender documentation makes bids comparable, so read this guide to procurement methods before you select yours.

  • Your part: select the contractor for scope and programme and not price.
  • Approval Checkpoint: You sign the contract award.
  • Inquire of your architect: How will you keep your bids within my spending plan?
  • Common error: comparing only totals. A low total can mask the lack of scope.

Phase 7: Construction Administration

The architect’s work is not over, the drawings are only finished. The architect is making observations during construction, reviewing submittals and shop drawings responding to questions from the contractor and auditing payment applications. The architect also issues change orders, reviews the punch list and certifies “substantial completion” as Open Exam Prep explains based on AIA B101 section 3.6. This is the 20 to 25% of the fee in the breakdown of Bob Vila.

Our Building Construction Services team constructs according to the approved design and robust monitoring and control ensure that the build remains on budget and on track.

  • Your duties: To make changes and payments in writing to attend site meetings.
  • Approval checkpoint: Signing of change orders and payment certificates.
  • Inquire from your architect: How many times will you be on site? How will you notify of problems?
  • Common error: failing to have meetings at the site. The MacLeamy curve depicts that problems discovered late are more expensive to correct.

Design Approval Checkpoints

Approval checkpoints help you keep your budget and your schedule. Each checkpoint makes a discussion into a written decision. If signed checkpoints are reopened, the team redraws work, re-checks costs and resubmits documents which will add weeks.

Checkpoint What you sign What reopening it costs you
Brief approval Purpose, space schedule, budget and programme A new concept and a fresh cost check
Concept approval One schematic option with its cost estimate Redrawn plans and elevations
Design freeze Materials, structure and building systems Revisions across every discipline
Documentation sign-off Full drawing set and specifications Reissued drawings, tender addenda or change orders
Permit authorisation Permit drawings and submission A repeat submission and a longer wait
Contract award Contractor, price and programme Re-tendering or contract variations

Arrange how many rounds of revisions will take place for each phase of the process in your appointment. Once approved, major changes incur a fee, as Fontan Architecture points out, so ask your architect how he is being treated by the appointment.

Client Responsibilities During The Design Process

A good design is only as good as a good client. These are the habits that help to maintain the process quickly:

  • Identify a decision maker who can say yes from the client side.
  • Share a clear brief and budget before the first sketch.
  • Provide land documents early, such as ownership documentation, site plan and previous surveys.
  • Set a time frame for answering design questions, e.g., 5 working days.
  • Always sign approvals and retain a copy.
  • Maintain a running list of open decisions with the architect and check it weekly.
  • Be sure to pay milestone bills on time to keep momentum going.
  • Participate in construction site meetings and address concerns on the day.

What Happens After the 7 Phases? Post-Construction and Building Evaluation

Strong projects are followed up with post-construction support and building evaluation after handover. This is Stage 7, “in use”, as called by RIBA and is used to assess the performance of the building. Architecture Courses identifies seven phase guides that drop permits and reference project post-occupancy review as the seventh phase. Both are the same trip but with different narrations. Only the grouping changes.

The handover includes as-built drawings, operation and maintenance manuals, warranties, and the completion certificate. After completing the handover, the project team conducts a post-occupancy evaluation focusing on three aspects:

  • Energy use and occupant comfort
  • Maintenance problems and defects
  • Feedback from members on layout and function.

How Long Does the Architectural Design Process Take?

According to Build Zoom, the typical range for the four basic design phases for a small residential project takes about 10 to 20 weeks or longer. For larger commercial projects, the time for each phase may be months. For example, Board & Vellum estimates that schematic design and contractor selection for a commercial project takes 2 to 4 months. Construction and Permits contribute to the total.

Phase Typical duration (small residential) What slows it down
Pre-design 1 to 3 weeks Missing land documents, an unclear budget
Schematic design 2 to 4 weeks Too many options, slow concept approval
Design development 3 to 6 weeks Late finish choices, consultant coordination
Construction documentation 4 to 8+ weeks Open design decisions, large or complex scope
Building permits 3 to 10 working days of municipal processing in Oman, plus other approvals Incomplete drawings, missing utility or Civil Defence approvals
Bidding and negotiation Varies with tender size and number of bidders Unclear tender documents, scope gaps
Construction administration Matches the construction period Late changes, weather, material delivery

Common Challenges During the Architectural Design Process

Most delays start at handoffs between phases. When scope creep happens, so do the earlier decisions that remain unlocked and each unanswered design development question ends up in construction documentation, Factorapp finds. Be alert to these challenges:

  • Budget mismatch: the brief requires more than the budget provides.
  • Scope creep: new requests are received after approval.
  • Approval delays: the team stalls with unanswered questions.
  • Coordination gaps: there are disagreements between structure, MEP and architecture on paper or on site.
  • Acceptance of rejections: If the drawings are not complete, they must be resubmitted.
  • Surprises in the procurement: scope is not covered by the bids because it is omitted from the drawings.

Use these five habits to protect your project: sign all approvals in writing, maintain an active list of pending decisions, freeze the scope before completing design development, appoint one client decision-maker, and review the project every week. Delays also build up outside of the design office, so before the build begins, read our tips on the 5 Challenges in Construction Project Management.

Common Design Mistakes to Avoid

  • Rushing pre-design. Fix: spend the time to write a complete brief.
  • Approving concepts informally. Fix: sign every approval with the cost estimate attached.
  • Changing finishes late. Fix: freeze materials at the end of design development.
  • Starting documentation with open decisions. Fix: run a closeout check first.
  • Ignoring local climate. Fix: design orientation, shading and insulation from day one.
  • Skipping cost checks. Fix: ask for a cost estimate at every phase.
  • Comparing bid totals only. Fix: compare scope, exclusions and programme line by line.
  • Skipping site supervision. Fix: keep the architect involved through construction.

How Technology Improves the Architectural Design Process

How technology improves the architectural design process through BIM, 3D architectural visualization, and project management software.

There are three tools that are most important. For architectural designs

BIM in Architecture

Building Information Modelling (BIM) creates one coordinated 3D model with information for all disciplines. According to the NBS Digital Construction Report 2025, approximately 7 in 10 construction professionals (72.3%) are currently using BIM and this has remained unchanged over the last seven years. The BIM overlay from RIBA has been rolled into the 2020 plan of work. This workflow is supported by our Building Information Modelling service covering the entire design process from concept to handover. BIM can assist in all phases:

  • Schematic design: model massing and check area targets.
  • Design development: detect clashes between structure and MEP.
  • Construction documentation: generate architectural drawings from one coordinated model.
  • Bidding: extract quantities for pricing.
  • Construction administration: compare site progress with the model.

3D Architectural Visualization

Realistic renders, walkthroughs and virtual reality tours enable you to grasp the design as you will experience it. Early viewing lets clients make quicker and more confident approvals with fewer late changes.

Project Management Software

Drawings, approvals and questions are all on a single platform, targeting the miscommunication that leads to the majority of rework. Check out our Architects’ Project Management Software guide for comparisons.

Important Considerations for Architectural Design Projects in Oman

The building market is a true opportunity in Oman. The market is expected to reach USD 7.27 billion by 2026, according to Mordor Intelligence. The market was largest for the residential segment with a 32.10% share followed by Muscat at 40.92%. All designs remain influenced by their surroundings and climate.

Oman Building Code Timeline

The Ministry of Housing and Urban Planning (MoHUP) has developed Oman’s first national building code with the International Code Council (ICC). The code family includes requirements related to building, energy efficiency and sustainability, mechanical, plumbing, private sewage disposal and existing and heritage buildings. In October of 2025, officials gave details of this rollout to Muscat Daily:

  • 2026–2027: voluntary adoption for training and feedback.
  • 2028: gradual enforcement begins in Muscat governorate.
  • 2030: mandatory compliance for all new buildings nationwide.

Building permits and authority approvals in Oman

According to the Ministry of Interior’s technical services page it takes 3 to 10 working days to get a building permit from a municipality. This number is for processing by the municipality. The application includes:

  • Architectural and structural maps
  • Utility approvals, including Omantel, Ooredoo and the Public Authority for Electricity and Water
  • Maps that the Public Authority for Civil Defence and Ambulance approves
  • A soil test report
  • Approvals from other government bodies

Climate, site and cultural design factors

  • Heat: orient the building, shade openings and insulate the envelope to cut cooling loads. Oman Observer reported that a 2013 scoping study found single glazing in 70% of homes, so glazing choices offer large savings.
  • Rain and wadis: plan site levels, drainage and flood paths for storm events, especially near wadis.
  • Coastal and Dhofar conditions: select materials that resist humidity, salt and monsoon moisture.
  • Family and culture: plan majlis placement, privacy, separate entrances and room for future extensions.

Project example: A Family villa in Muscat (illustrative)

This illustration shows how the phases overlap in a typical 450 sqm, two-storey family villa in Muscat. The durations follow the ranges listed above.

Phase What happened Outcome
Pre-design (2 weeks) The family supplied ownership documents and the plot plan, listed six bedrooms and a majlis, and set a budget ceiling. Family signs the brief
Schematic design (3 weeks) The architect presented three layouts with 3D visualizations and cost estimates. The family chose option B
Design development (5 weeks) The team coordinated structure and MEP in a BIM model and spotted a duct clash under the majlis. The family moved the majlis entrance before the design freeze. Family signs the design freeze
Construction documentation (7 weeks) The team produced architectural drawings, structural and MEP sheets, schedules and specifications. Client signs off the set
Building permits The consultant submitted the application with utility and Civil Defence approvals. Municipal processing took 8 working days. Municipality issues the permit
Bidding (4 weeks) Three contractors priced the same tender package. The team compared scope line by line and rejected the lowest bid for missing items. Client awards the contract
Construction administration The architect visited the site fortnightly, reviewed submittals and certified payments. Handover with as-built drawings

The lesson: the family experienced the majlis change during design development which had not yet involved rebuilding the structure but rather just a few model edits.

How to Choose the Right Architectural Design Company in Oman

Select a company with experience in guiding clients through all 7 phases and that understands the ins and outs of working with the authorities in Oman. Don’t sign until you have checked these points:

  • Local permit experience: ask how many municipal submissions the firm has handled and how it manages utility and Civil Defence approvals.
  • Full-service coverage: architecture, structure, MEP, cost control, supervision and construction under one roof reduce handoff errors.
  • Technology: confirm the firm uses BIM and 3D architectural visualization.
  • Clear fee structure: ask for a fee split by phase.
  • Relevant portfolio: look for projects like yours in size and type.
  • Written approvals and regular reporting: ask how the firm records decisions.
  • Quality systems: look for recognised certifications. Delta Gulf Overseas holds ISO 9001, ISO 45001 and ISO 14001 certifications.

Which Phases should You Hire an Architect for?

It is not necessary to purchase all phases. Planning Signal identifies three types of packages in RIBA terms:

  • Design and planning only: RIBA stages 1 to3.
  • Design by tender: stages 1 to 4, including technical drawings.
  • Full service: administration of the site in addition to stages 1 to 6.

If the building is complex or of high value, opt for full service. Site supervision safeguards your design intent.

Need Expert Architectural Guidance?

Get the right architectural support at every stage of your project, from initial planning to final construction.


Book a Consultation

How Much Does the Architectural Design Process Cost?

The architect’s fee is often between 5% and 15% of the total cost of construction. Illustrarch says it is that range; Bob Vila says it is 5% to 20%. The number changes depending on the region, project type and terms of the appointments. The fee increases are: Different design options, physical models or more advanced 3D representations, changes after approval and additional visits on site during construction. You still have budget certainty with a fixed fee but it will be more difficult for the architect to provide an estimate, says HomeAdvisor.

Looking to build a new construction in Oman? Check out our Architectural Design Services and Building Construction Services or give us a call to discuss your brief.

Frequently Asked Questions About the Architectural Design Process

How many stages are there in the architectural design process?

It depends on the frame of reference. There are five phases at AIA, eight stages at RIBA and numerous firms use seven phases. The seven-phase model is ideal for clients as it adds pre-design and building permits.

Which phase is the most expensive?

The most expensive type of construction documentation is approximately 40% of the fee and it is construction documentation. Construction administration comes next at 20 to 25%.

How long does it take for the building permit to come in Oman?

On the Ministry of Interior’s technical services page, it takes 3 to 10 working days for the municipality to issue a building permit. Utility, Civil Defence, and other authorities may require additional time to grant approvals.

Is there a national building code in Oman?

Yes. MOHP is implementing the Oman Building Code. In 2026-2027, adoption is voluntary, enforcement will begin incrementally in Muscat in 2028 and compliance will be enforced for new buildings across the country by 2030.

What is the difference between Schematic Design and Design Development?

The architect establishes the concept and layout during schematic design. Design development involves selecting materials, structure and building systems.

What is included in construction administration?

Construction administration includes working with site observation, submittal review, contractor inquiries, payment verifications, change orders, punch list and certification of substantial completion.

Is it possible to move from one phase to another?

For small projects, you can “shortcut” phases. There is an increased risk and cost of not documenting or obtaining permits.

When Do You Need a Contractor?

The traditional design-bid, build delivery process involves hiring a contractor post-bid. MasterClass states that the contractor participates in the construction documentation phase of design-build projects.